Scope

The following briefly summarises the key points of the recommended horizontal assembly and erection procedure for a gantry structure.

Generally, for relatively small poles, horizontal joint assembly followed by erecting the fully assembled structure is preferable. However, when structures are large or are to be replaced under an existing line, vertical assembly and erection may be more suitable.

Methodology

The key points for mid-flange jointed horizontal assembly and erection of the gantry in one piece are outlined below.

Phase 1: Preparation & Site Setup

  1. First, refer to pole approval drawings for pole details and correct orientation of the pole sections. Confirm all bolts, nuts, and washers are at hand for the assembly.
  2. At the site, arrange the base section on packing so that it is in the vicinity of the already prepared concrete foundation (for a base plate mounted pole).
  3. Ensure the base section is secure and the joint end is clear of the ground and supported on timber gluts. Furthermore, pole section identification plates should be orientated so that they are visible on the top face.

Phase 2: Pole Section Assembly

  1. After reviewing the drawings and the pole sections, bring the new section up to the joint flange, being careful to correctly orient and align the new piece. Next, install four bolts (including flat washers) at 90 degrees apart, screwing them up at least finger tight. Bolts should face downwards. Install remaining bolts, ensuring fingers are not pinched or trapped in the process.
  2. Snug tighten down all first-row nuts in a diametrically opposite sequence. Then, screw on the lock nuts to all bolts, snug tightening in a diametrically opposite sequence.
  3. Approximate bolt torque values for the snug tight condition are:
    1. M16 = 73Nm (or 54lbft)
    2. M20 = 143Nm (or 106lbft)
    3. M24 = 248Nm (or 183lbft)
    4. M30 = 491Nm (or 362lbft)
  4. Check that the assembled pole sections are in true alignment.
  5. Continue with the next bolted joint as described above until the pole is fully assembled.
  6. Finally, attach any accessories or brackets to the pole as deemed satisfactory according to the safe work method statement prepared for the pole erection.

Phase 3: Pre-Lift Setup & Safety

  1. Each pole features a lifting lug welded to the pole cap plate, intended as the primary lifting point for erecting the pole.
  2. For base plate mounted poles, prepare for erection by removing the top anchor bolt template from the foundation, including the top two nuts and one washer off each foundation anchor bolt. Of the remaining nuts, raise four of the foundation anchor bolt nuts 10mm above the rest at 90 degrees to each other and level them. The pole base plate will rest on these.
  3. Crucially, review safety considerations prior to any pole lift. Each site must determine, document, and train its personnel in safe work methods relevant to the site and to the pole assembly and installation.
  4. Always check all lifting tackle to ensure it is serviceable and adequate for the weight of the pole being lifted.

Phase 4: Erection & Foundation Attachment

  1. Now, carefully raise the pole to its full height and manoeuvre it onto the foundation bolts. Put on the 4 washers first and screw on the 4 top nuts corresponding to the 4 raised nuts. Snug tighten down the 4 top nuts in a diametrically opposite sequence.
  2. Snug tighten the 4 underside nuts as well, and then check the pole alignment in two directions at 90 degrees to one another. If satisfactory, continue to put the rest of the washers and top nuts on the anchor bolts.
  3. Bring the remaining nuts on the underside of the baseplate up tight against the baseplate. Snug tighten down all top nuts in a diametrically opposite sequence, followed by the underside nuts in a similar sequence. Recheck the top nuts. Finally, apply the lock nuts to all foundation bolts, snug tightening in a diametrically opposite sequence (refer to the torque values in Step 6).
  4. Check the final pole alignment and, if satisfactory, remove the lifting sling.
  5. Repeat this entire process for the second pole of the gantry.

Phase 5: Cross Beam Assembly

  1. Verify that the distance between the gantry cross beam mounting holes on the erected poles agrees with the assembled gantry beam attachment hole distance.
  2. The assembled 19m cross beam features a lifting point toward either end of the gantry for lifting it into position.
  3. Once positioned, ensure the crossbeam connection to pole bolts are snug tightened.